Development & property
54 containers in four months
2015—2017 · Cape Town
R85m
Phase 1 investment
127 units
Expanded from the first 54
The situation
Philippi is an under-served part of Cape Town. The brief was a mixed-use precinct that put commercial, retail, community and recreational space in one place — and the Industrial Development Corporation was funding it, at R85m for phase one, with a development mandate attached that went well beyond floor space.
Two things made it unusual. The first was the method: two-storey retail and services built from shipping containers, services above and retail below. The second was that the tenants were part of the deliverable. The IDC's mandate was entrepreneur incubation with a three-year path to self-sufficiency, so the project was not finished when the units were finished.
I was the project manager, contracted through Yoros.
What I did
I owned budget and cost control, building compliance and certification sign-off, and site health and safety across every contractor and trade on site. I reported to the IDC and the developer as the principal stakeholders — progress, risk and spend.
Containers were chosen because they are quicker and cheaper to build with than a conventional concrete building, which would have taken about three times longer. That decision shaped everything downstream. Modular construction moves the difficulty from the build to the sequencing: the units arrive fast, so services, compliance and fit-out become the critical path rather than the structure.
Alongside the build I ran tenant onboarding through the incubation model — fifteen entrepreneurs at a time, against the IDC's three-year mandate. That is a different kind of work to construction management and it ran concurrently, not afterwards.
What changed
The first 54-container precinct was delivered in four months — roughly a third of the time conventional construction would have taken. It then expanded to 127 units.
The tenants are the part worth stating plainly, because a retail precinct with no traders in it is a car park. Key cutting, clothing, fabric, building materials, insurance, a barber, a fish-and-chip shop, alongside Abalimi Bezekhaya and the BETA Foundation.
GroundUp covered the expansion independently.
What I'd do differently
I would build a prototype first.
Nobody I could hire had built with containers before. The contractors were good at what they did, and what they did was conventional construction — which meant every detail that differed from a brick building had to be worked out on site, in sequence, against a deadline, with a budget that had no room in it for learning. There was no manual. We wrote one as we went, which is the expensive way to write one.
A single unit built properly first, taken apart and argued over, would have cost a few weeks. It would have bought back more than that in the fifty-three that followed, and it would have given the contractors something to work from rather than something to work out.
The instinct on a tight deadline is that you cannot afford the prototype. On a build with no precedent, the prototype is the thing that makes the deadline.